Pending Generation

Find out why some of your generation shows as Pending in M-RETS® by CleanCounts, and what to send so a system administrator can review it and issue your Certificates.

ℹ️ At a glance

  • Most pending generation failed the feasibility check. The amount you reported is higher than what your Generator's Nameplate Capacity and Capacity Factor say is possible.
  • Pending generation isn't issued. No Certificates are created until it's approved.
  • To get it reviewed, email your meter readings or a screenshot of your meter data acquisition system to the system administrators.

Why your generation is pending

Every generation upload is checked automatically before Certificates are created. This check, called the Data Feasibility Validation, makes sure that:

  • No generation entries overlap.
  • There are no gaps in the reported dates.
  • The amount reported is possible for the hours in the period, based on your Generator's Nameplate Capacity and Capacity Factor.

If a vintage doesn't pass, it's marked Pending: Capacity Feasibility and held until a system administrator validates it.

How the feasibility limit is calculated

M-RETS uses this formula to work out the most generation that's feasible for a reported period. It allows a 2% margin above the expected amount.

Nameplate Capacity × Capacity Factor × Hours in the period × 1.02

For example, for a 2 MW Generator with a 25% Capacity Factor in a 30-day month:

Nameplate Capacity Capacity Factor Hours Feasible limit
2 MW 0.25 720 367.2 MWh

If you report more than 367.2 MWh for that month, the generation goes to Pending.

☀️ Solar and wind Generators

An average Capacity Factor can flag your strongest months as Pending, even when the data is correct, because output changes with the seasons. If this keeps happening, see Stop it from happening again below.

Get your pending generation reviewed

A system administrator needs evidence that your reported generation is accurate before approving it.

1

Gather documentation that supports the generation you reported, for example:

  • Meter readings for the period.
  • Screenshots of your meter data acquisition system showing the generation.
2

Email [email protected] and include:

  • The Generator name and M-RETS ID.
  • The pending vintage or vintages.
  • Your supporting documentation.
3

A system administrator reviews your data. Once it's approved, Certificates are issued into your issuance Account, and you'll get an email notification if your settings allow it.

Important: Don't re-upload the same generation to try to clear the Pending status. Uploading again can create overlapping entries. If the reported amount is wrong, email us and we'll help you correct it.

Stop it from happening again

When there's enough data, a system administrator can recommend an updated Capacity Factor for your Generator.

For Generators with seasonal output, like solar and wind, an administrator can review your historic meter data, model a monthly Capacity Factor, and add a Validation Curve. This makes the feasibility check more accurate across the year, so correct data in high-output months is less likely to go to Pending.

Other reasons generation can be pending

Feasibility isn't the only reason. Check which status you see on the Generation dashboard:

Reason What to do
Failed feasibility Send supporting documentation, as described above.
Waiting for a fuel split (multi-fuel Generators) Enter the fuel type allocation. See Entering a Fuel Split for Multi-Fuel Generators.
In the 14-day Holding Period Review and approve the generation. If no one reviews it within 14 days, Certificates are issued automatically.
Outside the upload window Generation older than the allowed window needs CleanCounts approval and may need a Generation Variance Request Form.

Need more help?

💬 Email the CleanCounts system administrators at [email protected] or call 651-900-7891.

📘 Read the full requirements in the Electricity Registry Operating Procedures.


This article is based on the Electricity Registry Operating Procedures, Version 2024.3: creation of Certificates and Data Feasibility Validation (Section 4.5.1, p. 36); generation statuses (Section 4.4, p. 30); uploading time restrictions (Section 4.4.2, p. 33); and Holding Period issuances (Section 4.4.9).