Repowered Generators: Commenced Operation Date and Repower Date

Learn which date to use as the Commenced Operation Date (COD) when a generator in the M-RETS® by CleanCounts Fuels Registry is repowered, refurbished, or expanded, and what you need to update after the work is done.

In short: a repower doesn't change your generator's COD. The COD always stays the date the facility originally began operating. You still need to tell CleanCounts about the repower and update any generator details that changed.

Need help? Email the CleanCounts system administrators at [email protected].

Commenced Operation Date vs. Repower Date

The Operating Procedures (Appendix B: Glossary) define the COD as the month and year a generator first began commercial operation. For non-commercial facilities, it's the date approved by the licensing or permitting agency.

Situation Commenced Operation Date to use
New generator The date it first began commercial operation
Repowered generator The original operation date, not the repower date
Refurbished generator The original operation date, not the refurbishment date
Added (incremental) capacity The original operation date of the existing capacity

The repower date is a separate piece of information. It records when the repowered equipment went into service, but it doesn't replace the COD.

Important: Don't change the Commenced Operation Date on your generator registration to the repower date. CleanCounts will keep the original COD on the record.

Step 1: Notify CleanCounts Within 30 Days

Under Section 4.3.6 (Changes to Static Data) of the Operating Procedures, you must notify CleanCounts within 30 calendar days of a change to any essential generating characteristics. A repower usually counts as this kind of change.

Email [email protected] with:

  • The generator name and M-RETS ID
  • The date the repowered equipment went into service (the repower date)
  • A short description of what changed, such as equipment, production capacity, metering, or the pipeline connection

Step 2: Update the Generator Details and Documents

Update any generator information that the repower changed, and upload documents that support the changes. Depending on the work done, this might include:

  • Updated equipment specifications or a revised engineering report from a licensed professional engineer
  • An updated process flow diagram (single line gas diagram)
  • New revenue quality meter details, such as meter model, serial number, and a photo of the installed meter
  • Updated production capacity information
  • Updated interconnection or injection point documentation, if the pipeline connection changed

Keep the Commenced Operation Date as it is.


What Happens Next

While CleanCounts reviews the changes, your generator moves to Pending status. After an administrator verifies the updates, the generator returns to Active.


Common Questions

  • Why doesn't the COD change after a repower? The COD reflects when the facility first began operating. The Operating Procedures say that for repowered or refurbished generators, the COD stays the original operation date.
  • We added production capacity. Is that a new generator? Not usually. Added capacity that's integrated into the existing facility keeps the original COD. For how CleanCounts defines a single facility, see Section 4.3.14 (Production Facility Boundary and Traceability).
  • Is there a fee? Changes to the common gas connection after registration must be reported and may be subject to a further registration fee (Section 4.3.14). Contact CleanCounts if you're unsure.
  • What if I miss the 30-day window? Email CleanCounts as soon as possible with the details above.